A Framework to Predict Time and Cost Risks based on Project Factors

Mohamad Hadi Jalili, Martin Skitmore

Abstract


The occurrence and severity of risks are directly associated with the project factors, and in the case of determining a logical and significant correlation between project factors and risks, the final conditions of the project based on the initial and definite project factors can be predicted. In this research, a final list of 112 risks was prepared using the views of experts. Then, the risks’ weight was determined based on their impact on time and cost and according to the repetition of each risk in the earlier studies, as well as the use of 630industry experts using online web-based forms. Afterwards, 21 project factors that could affect the probability of occurrence and severity of risks related to time and cost were identified, and these factors were prioritized for each risk using the views of 25 experts. Then, applying the Pareto Principle, 14 project factors were identified. In all 4cases, including calculating the weight of risks in the technical literature as well as the experts’ views by time and cost, 14 selected factors were the same, but the weight and effects were different. The results indicate that considering these factors, the risks of time and cost increase from the initial estimate can be accurately predicted.


Keywords


Prediction; Time; Cost; Risk; Project Factors.

References


Rosenfeld, Y. “Root-Cause Analysis of Construction-Cost Overruns.” Journal of Construction Engineering and Management (2014), 140 (1) https://doi.org/10.1061/(ASCE)CO.1943-7862.0000789

Aziz, R.F., and A.A. Abdel-Hakim “Exploring delay causes of road construction projects in Egypt.” Alexandria Engineering Journal (2016), 55, 1515-1539, http://dx.doi.org/10.1016/j.aej.2016.03.006

Noorzai, E., A. Hoseini, K. Gharouni Jafari, and M. Aghaeipoor “Providing a Model to Select an Optimum Multifamily Housing Method in Iran.” J. Archit. Eng. (2016), 23(2), 10.1061/(ASCE)AE.1943-5568.0000236

Torp, O., A.M. Belay, C. Thodesen, and O.J. Klakegg “Cost Development Over-time at Construction Planning Phase: Empirical Evidence from Norwegian Construction Projects.” International Conference on Sustainable Design, Engineering and Construction, Procedia Engineering (2016), 145, 1177 – 1184

Rybka, I., E. Bondar-Nowakowska, and M. Polonski “Cost Risk in Water and Sewerage Systems Construction Projects.” World Multidisciplinary Civil Engineering-Architecture-Urban Planning Symposium 2016, WMCAUS 2016, Procedia Engineering (2016), 161 ( 2016 ) 163 – 167

Noorzai, E., K. Gharouni Jafari, M Golabchi, S. Hamedi “Selecting an Appropriate Finance Method of Public-Private Partnership for Railway Projects in Iran through AHP Method.” International Conference on Civil Engineering-ICCEN, Auckland, New Zealand, Proceeding on International Journal of Structural and Civil Engineering Research, 5(1), (2015)

Qazi, A., J. Quigley, A. Dickson, and K. Kirytopoulos “Project Complexity and Risk Management (ProCRiM): Towards modelling project complexity driven risk paths in construction projects.” International Journal of Project Management (2016), 34 (2016) 1183–1198, http://dx.doi.org/10.1016/j.ijproman.2016.05.008

Yang, R.J., P.X.W. Zou, and J. Wang “Modelling stakeholder-associated risk networks in green building projects.” International Journal of Project Management (2015), 34(1), 66-81, https://doi.org/10.1016/j.ijproman.2015.09.010

Zhao, D., A.P. McCoy, B.M. Kleiner, T.H. Mills, and H. Lingard “Stakeholder perceptions of risk in construction.” Safety Science (2016), 82, https://doi.org/10.1016/j.ssci.2015.09.002

Taillandier, F., P. Taillandier, E. Tepeli, D. Breysse, R. Mehdizadeh, and F. Khartabil “A multi-agent model to manage risks in construction project (SMACC).” Automation in Construction (2015), 58, https://doi.org/10.1016/j.autcon.2015.06.005

Pressoir, S. "Are You Contracting for Success?" American Association of Cost Engineers (AACE), International's Professional Practice Guide to Contracts and Claims, AACE Transactions. Morgantown, WV, (1992)

Sambasivan, M., and Y.W. Soon “Cause and effects of delays in Malaysian construction industry.” International Journal of Project Management (2007), 25 (5), 517-526, https://doi.org/10.1016/j.ijproman.2006.11.007

Zhang, S., C. Du, W. Sa, C. Wang, and G. Wang “Bayesian-Based Hybrid Simulation Approach to Project Completion Forecasting for Underground Construction.” Journal of Construction Engineering and Management (2014), 140 (1), https://doi.org/10.1061/(ASCE)CO.1943-7862.0000764

Narbaev, T., and A. De Marco “Combination of Growth Model and Earned Schedule to Forecast Project Cost at Completion.” Journal of Construction Engineering and Management (2014), 140 (1), https://doi.org/10.1061/(ASCE)CO.1943-7862.0000783

Jiang, H., Y. Xu, and C. Liu “Construction Price Prediction Using Vector Error Correction Models.” Journal of Construction Engineering and Management (2013), 139(11), https://doi.org/10.1061/(ASCE)CO.1943-7862.0000729

Lhee, S.C., R.R.A. Issa, and I. Flood “Prediction of Financial Contingency for Asphalt Resurfacing Projects using Artificial Neural Network.” Journal of Construction Engineering and Management (2012), 138 (1), https://doi.org/10.1061/(ASCE)CO.1943-7862.0000408

Anastasopoulos, P.C., S. Labi, A. Bhargava, and F.L. Mannering “Empirical Assessment of the Likelihood and Duration of Highway Project Time Delays.” Journal of Construction Engineering and Management (2012), 138 (3), https://doi.org/10.1061/(ASCE)CO.1943-7862.0000437

Kim, J.L., and R.D. Ellis “Accurate cost contingency model for transportation construction projects.” TRB 2006 Annual Meeting (2006)

Zaneldin, E.K. “Construction claims in United Arab Emirates: Types, causes, and frequency.” International Journal of Project Management (2006), 24(5), https://doi.org/10.1016/j.ijproman.2006.02.006

Skitmore, R.M., and S.T. Ng “Forecast models for actual construction time and cost.” Building and Environment (2003), 38(8) https://doi.org/10.1016/S0360-1323(03)00067-2

Gonzalez, P., V. Gonzalez, K. Molenaar, F. Orozco “Analysis of Causes of Delay and Time Performance in Construction Projects.” Journal of Construction Engineering and Management (2014), 140(1) https://doi.org/10.1061/(ASCE)CO.1943-7862.0000721

Aziz, R.F. “Ranking of delay factors in construction projects after Egyptian revolution.” Alexandria Engineering Journal (2013), 52(3), https://doi.org/10.1016/j.aej.2013.03.002

Gosling, J., M. Naim, and D. Towill “Identifying and categorizing the sources of uncertainty in construction supply chains.” Journal of Construction Engineering and Management (2013), 139(1), doi: 10.1061/(ASCE)CO.1943-7862.0000574

Doloi, H. “Cost Overruns and Failure in Project Management: Understanding the Roles of Key Stakeholders in Construction Projects.” Journal of Construction Engineering and Management (2013), 139 (3), https://doi.org/10.1061/(ASCE)CO.1943-7862.0000621

Minchin Jr., R.E., X. Li, R.R. Issa, and G.G. Vargas “Comparison of Cost and Time Performance of Design-Build and Design-Bid-Buil Delivery Systems in Florida.” Journal of Construction Engineering and Management (2013), 139 (10), https://doi.org/10.1061/(ASCE)CO.1943-7862.0000746

Fallahnejad, M.H. “Delay causes in Iran gas pipeline projects.” International Journal of Project Management (2013), 31 (1), https://doi.org/10.1016/j.ijproman.2012.06.003

Subramanyan, H., P.H. Sawant, and V. Bhatt “Construction Project Risk Assessment: Development of Model Based on Investigation of Opinion of Construction Project Expert from India.” Journal of Construction Engineering and Management (2012), 138(3), https://doi.org/10.1061/(ASCE)CO.1943-7862.0000435

Yang, J.B., and P.R. Wei “Causes of Delay in the Planning and Design Phases for Construction Projects.” Journal of Architectural Engineering (2010), 16(2),

Hwang, B.G., M. Shan, and N.N.B. Supa’at “Green Commercial Building Projects in Singapore: Critical Risk Factors and Mitigation Measures.” Sustainable Cities and Society (2017), 30, 237-247, https://doi.org/10.1016/j.scs.2017.01.020

Farnsworth, C.B., R.O. Warr, J.E. Weidman, and D.M. Hutchings “Effects of CM/GC Project Delivery on Managing Process Risk in Transportation Construction.” Journal of Construction Engineering and Management (2016), 142(3), https://doi.org/10.1061/(ASCE)CO.1943-7862.0001091

Vrcek, N., P. Peharda, and D. Mundar “Methodology for risk assessment and corresponding costs in e-government project.” Faculty of Organization and Informatics, University of Zagreb (2015)

Gu, X., Z. Geng, W. Xu, and Q. Zhu “Hierarchy probability cost analysis model incorporate MAIMS principle for EPC project cost estimation.” Expert Systems with Applications (2011), 38(7), https://doi.org/10.1016/j.eswa.2010.12.150

Orangi, A., J. Palaneeswaran, and J. Wilson “Exploring Delays in Victoria-Based Australian Pipeline Projects.” The Twelfth East Asia-Pacific Conference on Structural Engineering and Construction, Procedia Engineering (2011), 14 (2011), https://doi.org/10.1016/j.proeng.2011.07.111

Idrus, A., M.F. Nuruddin, and M.A. Rohman “Development of project cost contingency estimation model using risk analysis and fuzzy expert system.” Expert Systems with Applications (2011), 38(3), https://doi.org/10.1016/j.eswa.2010.07.061

Hong, T.H., C.T. Hyun, and H.S. Moon “CBR-based cost prediction model-II of the design phase for multi-family housing projects.” Expert systems with applications (2011), 38 (3), https://doi.org/10.1016/j.eswa.2010.08.071

Lu, Y., X. Luo, and H. Zhang “A Gene Expression Programming Algorithm for Highway Construction Cost Prediction Problems.” Journal of Transportation Systems Engineering and Information Technology (2011), 11(6), https://doi.org/10.1016/S1570-6672(10)60150-X

Sweis, G., R. Sweis, A. Hmmad, and A. Shboul “Delays in construction projects: the case of Jordan.” International Project Management (2008), 26, 665-674.

Al-Kharashi, A., and M. Skitmore “Causes of delays in Saudi Arabian public sector construction projects.” Construction Management and Economics (2009), 27(1), 3-23.

El-Razek, M.E.A., H.A. Bassioni, and A.M. Mobarak “Causes of Delay in Building Construction Projects in Egypt.” Journal of Construction Engineering and Management (2008), 134, 831-841.

Aibinu, A.A., and H.A. Odeyinka “Construction delays and their causative factors in Nigeria.” Journal of Construction Engineering and Management (2006), 132(7), 667-677, https://doi.org/10.1061/(ASCE)0733-9364(2006)132:7(667)

Han, S.H., and K. Yun “Analyzing schedule delay of mega project: lessons learned from Korea Train Express.” IEEE Transactions on Engineering Management (2009), 56, 243-256.

Assaf, S.A., and S. Al-Hejji “Causes of delay in large construction projects.” International Journal of Project Management (2006), 24, 349-357.

Frimpong, Y., J. Oluwoye, and L. Crawford “Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study.” International Journal of Project Management (2003), 21, 321-326.

Odeh, A.M., and H.T. Battaineh “Causes of construction delay: traditional contracts.” International Journal of Project Management (2002), 20, 67-73.

Lo, T.Y., I.W.H. Fung, and K.C.F. Tung “Construction Delays in Hong Kong civil engineering projects.” Journal of Construction Engineering and Management (2006), 132, 639-642.

Elinwa, A.U., and M. Joshua “TIME-OVERRUN FACTORS IN NIGERIAN CONSTRUCTION INDUSTRY.” Construction Eng. & Management (2001), 127, 419-427.

Meduri, S.S., M. Tech, and T.R. Annamalai “Unit Costs of Public and PPP Road Projects: Evidence from India.” Journal of Construction Engineering and Management (2013), 139, 35-43.

Dikmen, I., M.T. Birgonul, J,H.M. Tah, and A.H. Ozer “Web-Based Risk Assessment Tool Using Integrated Duration-Cost Influence Network Model.” Journal of Construction Engineering and Management (2012), 138, 1023-1034

Choi, S., D.Y. Kim, S.H. Han, and Y.H. Kwak “Conceptual Cost-Prediction Model for Public Road Planning via Rough Set Theory and Case-Based Reasoning.” Journal of Construction Engineering and Management (2014), 140.

Senouci, A., A. Ismail, and N. Eldin “Time Delay and Cost Overrun in Qatari Public Construction Projects.” Pricedia Engineering (2016), 164, 368-375

El-Karim, M.S.B.A.A., O.A.M.E. Nawawy, and A.M. Abdel-Alim “Identification and assessment of Risk factors affecting construction projects.” HBRC Journal (2015)

Algahtany, M., Y. Alhammadi, and D. Kashiwagi “Introducing a New Risk Management Model to the Saudi Arabian Construction Industry.” Pricedia Engineering (2016), 145, 940-947

Khodeir, L.M., and A.H.M. Mohaned “Identifying the latest risk probabilistic affecting construction projects in Egypt according to political and economic variables, From January 2011 to January 2013.” HBRC Journal (2015), 11(1), 129-135, https://doi.org/10.1016/j.hbrcj.2014.03.007

Gharouni Jafari, K., E. Noorzai, S.R. Makkiabadi, and R. HeshmatNezhad “Providing a model to select a proper delivery system for railway projects in Iran.” ISAHP 2014 Conference – Washington DC

Golabchi, M., and E. Noorzai “Projects Delivery Methods.” Tehran University Press, 2013

Jin, R.Z., K.M. Cho, C.T. Hyun, and M.J. Son “MRA-based revised CBR model for cost prediction in the early stage of construction projects.” Expert Systems with Applications, 39(2012), doi:10.1016/j.eswa.2011.11.018


Full Text: PDF

DOI: 10.28991/cej-03091195

Refbacks

  • There are currently no refbacks.




Copyright (c) 2018 Mohamad Hadi Jalili, Abdollah Hosseini, Shahab Araghinejad

Creative Commons License
This work is licensed under a Creative Commons Attribution 4.0 International License.
x
Message