A Case Study of S-Curve Analysis: Causes, Effects, Tracing and Monitoring Project Extension of Time

Habib Musa Mohamad, Mohamad Ibrahim Mohamad, Ismail Saad, Nurmin Bolong, J. Mustazama, Siti Nooraiin Mohd Razali

Abstract


S-Curve analysis in the construction interpreted as managing project with knowledge and traceable in the context of sustainable construction while displays the cumulative costs, labour hours or other quantities plotted against time. In the contract administration, delays in completing a construction project led to the breach of contract but, in contracts itself allow the construction period to be extended where there are delays that are not the contractor's fault. Under those circumstances, a presentation of a case-study regarding the analysis of S-Curve of a life project drew comparative interpretation of project performance towards project delivery schedule has been conducted in private initiative project. This study aims to investigate and examine the factors that cause delays in construction projects from the perspective of S-curve representations. The paper aims to provide in depth light about the existing causes of project delay and describe the key sources of financing problem and identify the consequences of contraventions of contract. Two distinct parts divided which are refers to the methods used to assess the perceptions of clients, consultants, and contractors on the relative importance of causes of delay in a project and referred to the procurement and documentation to analyse the delay. As a result, an Extension of Time (EOT) granted and identically changed the progress towards extension time where better planning demanded for improvement and restoration progress kept on track. This paper presented a practical and comparative S-Curve within extension of time to ensure delivery of project on schedule. In the long run, the identified causes are combined into 16 factors. Finally, the result of this match was brought in order to critically understand and provide a guideline to contractor in preparing EOT application and choose reliable factor based on the specific circumstances of project delay factors thorough review conducted to reveal the nature of EOT application techniques.

 

Doi: 10.28991/cej-2021-03091679

Full Text: PDF


Keywords


S-Curve; Causes; Extension of Time; Monitoring Project; Management.

References


Hsieh, Ting-Ya, Morris Hsiao-Lung Wang, and Cheng-Wu Chen. "A case study of S-curve regression method to project control of construction management via TS fuzzy model." Journal of Marine Science and Technology 12, no. 3 (2004): 209-216. doi:10.6119/JMST.200409_12(3).0010.

Latham, M. “Report: Department of the Environment: Constructing the Team”, Her Majesty's Stationery Office - HMSO, London, 1994.

Emerson, H. “Report Ministry of Works: Survey of Problems before the Construction Industries”. Her Majesty's Stationery Office - HMSO, London, 1964.

Ramanathan, Chidambaram, S P Narayanan, and Arazi B Idrus. “Construction Delays Causing Risks on Time and Cost - a Critical Review.” Construction Economics and Building 12, no. 1 (February 26, 2012): 37–57. doi:10.5130/ajceb.v12i1.2330.

Okpala, Daniel C., and Anny N. Aniekwu. “Causes of High Costs of Construction in Nigeria.” Journal of Construction Engineering and Management 114, no. 2 (June 1988): 233–244. doi:10.1061/(asce)0733-9364(1988)114:2(233).

Levy, S. M. “Project Management in Construction”, McGraw-Hill, New York, NY, USA, p 478, 2012.

Chan, Daniel WM, and Mohan M Kumaraswamy. “A Comparative Study of Causes of Time Overruns in Hong Kong Construction Projects.” International Journal of Project Management 15, no. 1 (February 1997): 55–63. doi:10.1016/s0263-7863(96)00039-7.

Alnaas, Khaled Ahmed Ali, Ayman Hussein Hosny Khalil, and Gamal Eldin Nassar. “Guideline for Preparing Comprehensive Extension of Time (EoT) Claim.” HBRC Journal 10, no. 3 (December 2014): 308–316. doi:10.1016/j.hbrcj.2014.01.005.

Project Management Institute. “A Guide to the Project Management Body of Knowledge (Pmbok Guide)”, 5th ed.; Project Management Institute: Newtown Square, PA, USA, p. 616. 2013.

Alias, Zarina, Zarita Ahmad Baharum, and Muhammad Fahmi Md Idris. “Project Management Towards Best Practice”, Procedia - Social and Behavioral Sciences, AicE-Bs 2012 Cairo (Asia Pacific International Conference on Environment-Behaviour Studies), Mercure Le Sphinx Cairo Hotel, Giza, Egypt, (December 2012): 108–120. doi:10.1016/j.sbspro.2012.12.211.

Rui, Lee Mao, Syuhaida Ismail, and Mohammad Hussaini. “Professional Development of Project Management for Contractor in the Construction Project: A Review.” Procedia - Social and Behavioral Sciences 174 (February 2015): 2940–2945. doi:10.1016/j.sbspro.2015.01.1032.

Barnes, M. “Construction project management”, International Journal of Project Management, Volume 6, Issue 2, Pages 69-79, May, 1988.

Jaffar, N., A.H. Abdul Tharim, and M.N. Shuib. “Factors of Conflict in Construction Industry: A Literature Review.” Procedia Engineering 20 (2011): 193–202. doi:10.1016/j.proeng.2011.11.156.

Aziz, R. F. (2013). Ranking of delay factors in construction projects after Egyptian revolution. Alexandria Engineering Journal, 52(3), 387–406. doi:10.1016/j.aej.2013.03.002.

Cioffi, Denis F. "A tool for managing projects: an analytic parameterization of the S-curve." International Journal of Project Management 23, no. 3 (2005): 215-222. doi:10.1016/j.ijproman.2004.08.001.

Yoke-Lian, Lew, S. Hassim, R. Muniandy, and Tan Mee-Ling. "The assessment of applications for extension of time claims in Malaysian construction industry." International Journal of Engineering and Technology 4, no. 4 (2012): 446. doi: 10.7763/IJET.2012.V4.407.

Hamzah, Noraini, A. Ramly, H. Salleh, N. M. Tawil, M. A. Khoiry, and AI Che Ani. "The importance of design process in housing quality." 2nd International Building Control Conference Procedia Engineering 20 (2011): 483-489. doi: 10.1016/j.proeng.2011.11.191.

Akanni, P.O., A.E. Oke, and O.A. Akpomiemie. “Impact of Environmental Factors on Building Project Performance in Delta State, Nigeria.” HBRC Journal 11, no. 1 (April 2015): 91–97. doi:10.1016/j.hbrcj.2014.02.010.

Danuri, MS Mohd, ME Che Munaaim, H. Abdul Rahman, and M. Hanid. "Late and non-payment issues in the Malaysian Construction Industry-Contractor's perspective." In International Conference on Construction, Culture, Innovation and Management (CCIM), pp. 26-29. 2006.

Ye, Kho Mei, and Hamzah Abdul Rahman. "Risk of late payment in the Malaysian construction industry." International Journal of Mechanical and Industrial Engineering 4, no. 5 (2010): 503-511.

Wilder, J. "Guard yourself against construction risk." Hotel & Hotel Management 222, no. 21 (2007): 12.

Odeyinka, H. A., & Yusif, A. (1997). The causes and effects of construction delays on completion cost of housing projects in Nigeria. Journal of Financial Management of Property and Construction, 2, 31-44.

Nguyen, Long D., Jax Kneppers, Borja García de Soto, and William Ibbs. “Analysis of Adverse Weather for Excusable Delays.” Journal of Construction Engineering and Management 136, no. 12 (December 2010): 1258–1267. doi:10.1061/(asce)co.1943-7862.0000242.

Atkinson, Roger. “Project Management: Cost, Time and Quality, Two Best Guesses and a Phenomenon, Its Time to Accept Other Success Criteria.” International Journal of Project Management 17, no. 6 (December 1999): 337–342. doi:10.1016/s0263-7863(98)00069-6.

Yusuwan, Norazian Mohamad, and Hamimah Adnan. “Issues Associated with Extension of Time (EoT) Claim in Malaysian Construction Industry.” Procedia Technology 9 (2013): 740–749. doi:10.1016/j.protcy.2013.12.082.

Shahsavand, Parvaneh, Akbar Marefat, and Majid Parchamijalal. “Causes of Delays in Construction Industry and Comparative Delay Analysis Techniques with SCL Protocol.” Engineering, Construction and Architectural Management 25, no. 4 (May 21, 2018): 497–533. doi:10.1108/ecam-10-2016-0220.

K.V., Prasad, Vasugi V., Venkatesan R., and Nikhil Bhat. “Analysis of Causes of Delay in Indian Construction Projects and Mitigation Measures.” Journal of Financial Management of Property and Construction 24, no. 1 (April 1, 2019): 58–78. doi:10.1108/jfmpc-04-2018-0020.

Arantes, Amílcar, and Luís Miguel D.F. Ferreira. “Underlying Causes and Mitigation Measures of Delays in Construction Projects.” Journal of Financial Management of Property and Construction 25, no. 2 (February 26, 2020): 165–181. doi:10.1108/jfmpc-03-2019-0029.

Rooholelm, Vahid, and Abbas Sheikh Aboumasoudi. “Share Determination of Stakeholder Delays, Based on Targeted Delay Analysis of Projects, with Incursive and Defensive (In-De) Approach.” International Journal of Managing Projects in Business 13, no. 6 (July 1, 2020): 1219–1261. doi:10.1108/ijmpb-08-2019-0196.

Ahmad, Hesham S., Maha D. Ayoush, and Majed S. Al-Alwan. “Causes of Delay to Public Infrastructure Projects According to Engineers Representing Different Contract Parties.” Built Environment Project and Asset Management 10, no. 1 (December 17, 2019): 153–179. doi:10.1108/bepam-03-2019-0026.

Zailani, Suhaiza, Hazrina Aziz Md. Ariffin, Mohammad Iranmanesh, Soroush Moeinzadeh, and Masoomeh Iranmanesh. “The Moderating Effect of Project Risk Mitigation Strategies on the Relationship Between Delay Factors and Construction Project Performance.” Journal of Science and Technology Policy Management 7, no. 3 (October 3, 2016): 346–368. doi:10.1108/jstpm-12-2015-0041.

Elawi, Ghazi Saad A., Mohammed Algahtany, and Dean Kashiwagi. “Owners’ Perspective of Factors Contributing to Project Delay: Case Studies of Road and Bridge Projects in Saudi Arabia.” Procedia Engineering 145 (2016): 1402–1409. doi:10.1016/j.proeng.2016.04.176.

Marzouk, Mohamed M., and Tarek I. El-Rasas. “Analyzing Delay Causes in Egyptian Construction Projects.” Journal of Advanced Research 5, no. 1 (January 2014): 49–55. doi:10.1016/j.jare.2012.11.005.

Kazaz, Aynur, Serdar Ulubeyli, and Nihan Avcioglu Tuncbilekli. “CAUSES OF DELAYS IN CONSTRUCTION PROJECTS IN TURKEY.” Journal of Civil Engineering and Management 18, no. 3 (June 29, 2012): 426–435. doi:10.3846/13923730.2012.698913.

Odeh, Abdalla M, and Hussien T Battaineh. “Causes of Construction Delay: Traditional Contracts.” International Journal of Project Management 20, no. 1 (January 2002): 67–73. doi:10.1016/s0263-7863(00)00037-5.

Riazi, Salman Riazi Mehdi, and Mohd Nasrun Mohd Nawi. “Project Delays in the Malaysian Public Sector: Causes, Pathogens and the Supply Chain Management Approach.” International Journal of Technology 9, no. 8 (December 30, 2018): 1668. doi:10.14716/ijtech.v9i8.2758.

Ramli, M Z, M A Malek, M H Hanipah, C L Lin, M F Mahamad Sukri, M H Zawawi, M Z Zainal Abidin, and N F S Mohamad Fuad. “Study of Factors Influencing Construction Delays at Rural Area in Malaysia.” Journal of Physics: Conference Series 1049 (July 2018): 012017. doi:10.1088/1742-6596/1049/1/012017.

Othuman Mydin, M.A., N. Md Sani, M. Taib, and N. Mohd Alias. “Imperative Causes of Delays in Construction Projects from Developers’ Outlook.” Edited by Md A. Othuman Mydin. MATEC Web of Conferences 10 (2014): 06005. doi:10.1051/matecconf/20141006005.

Zainorabidin, Adnan, and Habib Musa Mohamad. "Preliminary peat surveys in ecoregion delineation of North Borneo: Engineering Perspective." Electronic Journal of Geotechnical Engineering 21, no. 12 (2016): 4485-4493.


Full Text: PDF

DOI: 10.28991/cej-2021-03091679

Refbacks

  • There are currently no refbacks.




Copyright (c) 2021 HABIB MUSA BIN MOHAMAD

Creative Commons License
This work is licensed under a Creative Commons Attribution 4.0 International License.
x
Message