Construction Project Delay Risk Assessment Based on 4M1E Framework and Afghanistan Situation
Abstract
Doi: 10.28991/CEJ-2024-010-01-06
Full Text: PDF
Keywords
References
Horta, I. M., Camanho, A. S., Johnes, J., & Johnes, G. (2013). Performance trends in the construction industry worldwide: An overview of the turn of the century. Journal of Productivity Analysis, 39(1), 89–99. doi:10.1007/s11123-012-0276-0.
Abdulfattah, B. S., Abdelsalam, H. A., Abdelsalam, M., Bolpagni, M., Thurairajah, N., Perez, L. F., & Butt, T. E. (2023). Predicting implications of design changes in BIM-based construction projects through machine learning. Automation in Construction, 155, 105057. doi:10.1016/j.autcon.2023.105057.
Wuni, I. Y., Shen, G. Q., & Hwang, B.-G. (2020). Risks of modular integrated construction: A review and future research directions. Frontiers of Engineering Management, 7(1), 63–80. doi:10.1007/s42524-019-0059-7.
Do, S. T., Nguyen, V. T., Tran, C. N. N., & Aung, Z. M. (2023). Identifying and evaluating the key claim causes leading to construction delays. International Journal of Construction Management, 23(12), 1999–2011. doi:10.1080/15623599.2022.2030508.
Genc, O. (2023). Identifying principal risk factors in Turkish construction sector according to their probability of occurrences: a relative importance index (RII) and exploratory factor analysis (EFA) approach. International Journal of Construction Management, 23(6), 979–987. doi:10.1080/15623599.2021.1946901.
Yong, Y. C., & Mustaffa, N. E. (2013). Critical success factors for Malaysian construction projects: An empirical assessment. Construction Management and Economics, 31(9), 959–978. doi:10.1080/01446193.2013.828843.
Olawale, Y. A., & Sun, M. (2010). Cost and time control of construction projects: Inhibiting factors and mitigating measures in practice. Construction Management and Economics, 28(5), 509–526. doi:10.1080/01446191003674519.
HYap, J. B. H., & Skitmore, M. (2017). Investigating design changes in Malaysian building projects. Architectural Engineering and Design Management, 14(3), 218–238. doi:10.1080/17452007.2017.1384714.
Mukuka, M., Aigbavboa, C., & Thwala, W. (2015). Effects of Construction Projects Schedule Overruns: A Case of the Gauteng Province, South Africa. Procedia Manufacturing, 3, 1690–1695. doi:10.1016/j.promfg.2015.07.989.
Gb, P. T., & Ajuwon, O. S. (2017). Effects of Project Cost Overruns and Schedule Delays in Sub-Saharan Africa. European Journal of Interdisciplinary Studies, 7(2), 46. doi:10.26417/ejis.v7i2.p46-59.
Sambasivan, M., Deepak, T. J., Salim, A. N., & Ponniah, V. (2017). Analysis of delays in Tanzanian construction industry Transaction cost economics (TCE) and structural equation modeling (SEM) approach. Engineering, Construction and Architectural Management, 24(2), 308–325. doi:10.1108/ECAM-09-2015-0145.
Amoatey, C. T., Ameyaw, Y. A., Adaku, E., & Famiyeh, S. (2015). Analysing delay causes and effects in Ghanaian state housing construction projects. International Journal of Managing Projects in Business, 8(1), 198–214. doi:10.1108/IJMPB-04-2014-0035.
Aibinu, A. A., & Jagboro, G. O. (2002). The effects of construction delays on project delivery in Nigerian construction industry. International Journal of Project Management, 20(8), 593–599. doi:10.1016/S0263-7863(02)00028-5.
Nepal, M. P., Park, M., & Son, B. (2006). Effects of Schedule Pressure on Construction Performance. Journal of Construction Engineering and Management, 132(2), 182–188. doi:10.1061/(asce)0733-9364(2006)132:2(182).
Yap, J. B. H., Rou Chong, J., Skitmore, M., & Lee, W. P. (2020). Rework Causation that Undermines Safety Performance during Production in Construction. Journal of Construction Engineering and Management, 146(9), 04020106. doi:10.1061/(asce)co.1943-7862.0001902.
Iqbal, S., Choudhry, R. M., Holschemacher, K., ALI, A., & Tamošaitienė, J. (2015). Risk Management in Construction Projects. Technological and Economic Development of Economy, 21(1), 65–78. doi:10.3846/20294913.2014.994582.
Alvand, A., Mirhosseini, S. M., Ehsanifar, M., Zeighami, E., & Mohammadi, A. (2023). Identification and assessment of risk in construction projects using the integrated FMEA-SWARA-WASPAS model under fuzzy environment: a case study of a construction project in Iran. International Journal of Construction Management, 23(3), 392–404. doi:10.1080/15623599.2021.1877875.
Pham, H. T., Pham, T., Truong Quang, H., & Dang, C. N. (2023). Supply chain risk management research in construction: a systematic review. International Journal of Construction Management, 23(11), 1945–1955. doi:10.1080/15623599.2022.2029677.
Shabani, R., Ishtiaque, T. A., Johansen, A., Torp, O., & Farsani, D. (2023). Uncertainty management in the design phase of road projects. Procedia Computer Science, 219, 1969–1976. doi:10.1016/j.procs.2023.01.497.
Niazi, G. A., & Painting, N. (2017). Significant Factors Causing Cost Overruns in the Construction Industry in Afghanistan. Procedia Engineering, 182, 510–517. doi:10.1016/j.proeng.2017.03.145.
Bhih, M., & Hegazy, T. (2021). Multiple-window Modified But-For analysis of project delays and accelerations. International Journal of Construction Management, 23(4), 686–696. doi:10.1080/15623599.2021.1916708.
Jahanger, Q. K. (2013). Important causes of delay in construction projects in Baghdad city. Australian Journal of Basic and Applied Sciences, 7(4), 14-23.
Bhih, M., & Hegazy, T. (2023). Multiple-window modified but-for analysis of project delays and accelerations. International Journal of Construction Management, 23(4), 686-696. doi:10.1080/15623599.2021.1916708.
Le-Hoai, L., Lee, Y. D., & Lee, J. Y. (2008). Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries. KSCE Journal of Civil Engineering, 12(6), 367–377. doi:10.1007/s12205-008-0367-7.
Abd El-Razek, M. E., Bassioni, H. A., & Mobarak, A. M. (2008). Causes of Delay in Building Construction Projects in Egypt. Journal of Construction Engineering and Management, 134(11), 831–841. doi:10.1061/(asce)0733-9364(2008)134:11(831).
Enshassi, A., Kumaraswamy, M., & Jomah, A. N. (2010). Significant factors causing time and cost overruns in construction projects in the gaza strip: Contractors’ perspective. International Journal of Construction Management, 10(1), 35–60. doi:10.1080/15623599.2010.10773137.
Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012). Analysing factors affecting delays in Indian construction projects. International Journal of Project Management, 30(4), 479–489. doi:10.1016/j.ijproman.2011.10.004.
Akogbe, R. K. T. M., Feng, X., & Zhou, J. (2013). Importance and ranking evaluation of delay factors for development construction projects in Benin. KSCE Journal of Civil Engineering, 17(6), 1213–1222. doi:10.1007/s12205-013-0446-2.
Muhwezi, L., Acai, J., & Otim, G. (2014). An assessment of the factors causing delays on building construction projects in Uganda. International Journal of Construction Engineering and Management, 3(1), 13-23.
Hussain, S., Zhu, F., Ali, Z., Aslam, H. D., & Hussain, A. (2018). Critical delaying factors: Public sector building projects in Gilgit-Baltistan, Pakistan. Buildings, 8(1), 6. doi:10.3390/buildings8010006.
Wang, T. K., Ford, D. N., Chong, H. Y., & Zhang, W. (2018). Causes of delays in the construction phase of Chinese building projects. Engineering, Construction and Architectural Management, 25(11), 1534–1551. doi:10.1108/ECAM-10-2016-0227.
Zidane, Y. J. T., & Andersen, B. (2018). The top 10 universal delay factors in construction projects. International Journal of Managing Projects in Business, 11(3), 650–672. doi:10.1108/IJMPB-05-2017-0052.
Li, X., Lu, W., Xue, F., Wu, L., Zhao, R., Lou, J., & Xu, J. (2022). Blockchain-Enabled IoT-BIM Platform for Supply Chain Management in Modular Construction. Journal of Construction Engineering and Management, 148(2), 04021195. doi:10.1061/(asce)co.1943-7862.0002229.
Rezgui, Y. (2007). Exploring virtual team-working effectiveness in the construction sector. Interacting with Computers, 19(1), 96–112. doi:10.1016/j.intcom.2006.07.002.
Kakar, A. S., Hasan, A., & Jha, K. N. (2020). Schedule Success Factors in Construction Projects in a War-Affected Region. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 12(3), 05020008. doi:10.1061/(asce)la.1943-4170.0000417.
Qaytmas, N. (2020). Causes of Delays in Construction Projects in Faryab/Afghanistan. International Journal for Research in Applied Sciences and Biotechnology, 7(6), 72–77. doi:10.31033/ijrasb.7.6.12.
Kakar, A. S., Hasan, A., Jha, K. N., & Singh, A. (2022). Project cost performance factors in the war-affected and conflict-sensitive Afghan construction industry. Journal of Engineering, Design and Technology, 1-21. doi:10.1108/JEDT-11-2021-0657.
Rao, P. B., & Joseph Camron, C. (2014). Causes of delays in construction projects-A case study. International Journal of Current Research, 6(6), 7219-7222.
Muneeswaran, G., Manoharan, P., Awoyera, P. O., & Adesina, A. (2020). A statistical approach to assess the schedule delays and risks in Indian construction industry. International Journal of Construction Management, 20(5), 450–461. doi:10.1080/15623599.2018.1484991.
Ejaz, N., Ali, I., & Tahir, M. F. (2011). Assessment of delays and cost overruns during construction projects in Pakistan. In Proceedings of the International Conference on Structural Engineering Construction and Management, Kandy, Sri Lanka, 16–18 December 2011. Available online: http://dl.lib.mrt.ac.lk/handle/123/9431 (accessed on December 2023).
Aibinu, A. A., & Odeyinka, H. A. (2006). Construction Delays and Their Causative Factors in Nigeria. Journal of Construction Engineering and Management, 132(7), 667–677. doi:10.1061/(asce)0733-9364(2006)132:7(667).
Obodoh, D. A., & Obodoh, C. (2016). Causes and effects of construction project delays in Nigerian construction industry. International Journal of Innovative Science, Engineering & Technology, 3(5), 65-84.
Alzara, M., Kashiwagi, J., Kashiwagi, D., & Al-Tassan, A. (2016). Using PIPS to Minimize Causes of Delay in Saudi Arabian Construction Projects: University Case Study. Procedia Engineering, 145, 932–939. doi:10.1016/j.proeng.2016.04.121.
Alinaitwe, H., Apolot, R., & Tindiwensi, D. (2013). Investigation into the causes of delays and cost overruns in Uganda's public sector construction projects. Journal of Construction in Developing Countries, 18(2), 33.
Motaleb, O., & Kishk, M. (2013). An Investigation into the Risk of Construction Projects Delays in the UAE. International Journal of Information Technology Project Management, 4(3), 50–65. doi:10.4018/jitpm.2013070104.
Choplin, A., & Franck, A. (2016). Seeing Dubai in Khartoum and Nouakchott: ‘Gulfication’ on the margins of the Arab world. Under Construction: Logics of Urbanism in the Gulf Region, 36(2), 271–284. doi:10.4324/9781315549323-37.
Alaghbari, W., Kadir, M. R. A., Salim, A., & Ernawati. (2007). The significant factors causing delay of building construction projects in Malaysia. Engineering, Construction and Architectural Management, 14(2), 192–206. doi:10.1108/09699980710731308.
Khan, R. A., Gazder, U., & Qayoom, A. (2017). Comparison of delay factors and remedies’ rankings for building construction projects in developing countries. International Journal of Advanced and Applied Sciences, 4(4), 33–42. doi:10.21833/ijaas.2017.04.006.
Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5), 517–526. doi:10.1016/j.ijproman.2006.11.007.
Samarghandi, H., Tabatabaei, S. M. M., Taabayan, P., Hashemi, A. M., & Willoughby, K. (2016). Studying the Reasons for Delay and Cost Overrun in Construction Projects: The Case of Iran. Journal of Construction in Developing Countries, 21(1), 51–84. doi:10.21315/jcdc2016.21.1.4.
Islam, M. S., & Trigunarsyah, B. (2017). Construction Delays in Developing Countries: A Review. Journal of Construction Engineering and Project Management, 7(1), 1–12. doi:10.6106/jcepm.2017.3.30.001.
Odeh, A. M., & Battaineh, H. T. (2002). Causes of construction delay: traditional contracts. International Journal of Project Management, 20(1), 67–73. doi:10.1016/s0263-7863(00)00037-5.
Sweis, G., Sweis, R., Abu Hammad, A., & Shboul, A. (2008). Delays in construction projects: The case of Jordan. International Journal of Project Management, 26(6), 665–674. doi:10.1016/j.ijproman.2007.09.009.
Al-Momani, A. H. (2000). Construction delay: a quantitative analysis. International Journal of Project Management, 18(1), 51–59. doi:10.1016/s0263-7863(98)00060-x.
Bagaya, O., & Song, J. (2016). Empirical Study of Factors Influencing Schedule Delays of Public Construction Projects in Burkina Faso. Journal of Management in Engineering, 32(5), 05016014. doi:10.1061/(asce)me.1943-5479.0000443.
Hsu, P. Y., Aurisicchio, M., & Angeloudis, P. (2017). Investigating Schedule Deviation in Construction Projects through Root Cause Analysis. Procedia Computer Science, 121, 732–739. doi:10.1016/j.procs.2017.11.095.
Marzouk, M. M., & El-Rasas, T. I. (2014). Analyzing delay causes in Egyptian construction projects. Journal of Advanced Research, 5(1), 49–55. doi:10.1016/j.jare.2012.11.005.
Toor, S.-U.-R., & Ogunlana, S. (2008). Problems causing delays in major construction projects in Thailand. Construction Management and Economics, 26(4), 395–408. doi:10.1080/01446190801905406.
Toor, S. ur R., & Ogunlana, S. O. (2008). Critical COMs of success in large-scale construction projects: Evidence from Thailand construction industry. International Journal of Project Management, 26(4), 420–430. doi:10.1016/j.ijproman.2007.08.003.
Choong Kog, Y. (2018). Major Construction Delay Factors in Portugal, the UK, and the US. Practice Periodical on Structural Design and Construction, 23(4), 4018024. doi:10.1061/(asce)sc.1943-5576.0000389.
Kazaz, A., Ulubeyli, S., & Tuncbilekli, N. A. (2012). Causes Of Delays in Construction Projects in Turkey. Journal of Civil Engineering and Management, 18(3), 426–435. doi:10.3846/13923730.2012.698913.
Cho, K., Ahn, S., Park, K., & Kim, T. W. (2021). Schedule Delay Leading Indicators in Precast Concrete Construction Projects: Qualitative Comparative Analysis of Korean Cases. Journal of Management in Engineering, 37(4), 4021024. doi:10.1061/(asce)me.1943-5479.0000915.
Chan, D. W. M., & Kumaraswamy, M. M. (1997). A comparative study of causes of time overruns in Hong Kong construction projects. International Journal of Project Management, 15(1), 55–63. doi:10.1016/S0263-7863(96)00039-7.
Chan, D. W. M., & Kumaraswamy, M. M. (2002). Compressing construction durations: Lessons learned from Hong Kong building projects. International Journal of Project Management, 20(1), 23–35. doi:10.1016/S0263-7863(00)00032-6.
Ling, F. Y. Y., & Poh, B. H. M. (2008). Problems encountered by owners of design-build projects in Singapore. International Journal of Project Management, 26(2), 164–173. doi:10.1016/j.ijproman.2007.04.001.
Hwang, B.-G., & Lim, E.-S. J. (2013). Critical Success Factors for Key Project Players and Objectives: Case Study of Singapore. Journal of Construction Engineering and Management, 139(2), 204–215. doi:10.1061/(asce)co.1943-7862.0000597.
Koushki, P. A., & Kartam, N. (2004). Impact of construction materials on project time and cost in Kuwait. Engineering, Construction and Architectural Management, 11(2), 126–132. doi:10.1108/09699980410527867.
Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349–357. doi:10.1016/j.ijproman.2005.11.010.
Hair, J. F., Black, W. C., Babin, B. J., & Anderson, R. E. (2019). Multivariate data analysis. Cengage Learning. Hampshire, United Kingdom.
Abdul-Aziz, A. R. (2012). Control mechanisms exercised in Malaysian housing public-private partnerships. Construction Management and Economics, 30(1), 37–55. doi:10.1080/01446193.2011.654129.
Nguyen, T. P., & Chileshe, N. (2015). Revisiting the construction project failure factors in Vietnam. Built Environment Project and Asset Management, 5(4), 398–416. doi:10.1108/BEPAM-10-2013-0042.
Yap, J. B. H., Chow, I. N., & Shavarebi, K. (2019). Criticality of Construction Industry Problems in Developing Countries: Analyzing Malaysian Projects. Journal of Management in Engineering, 35(5), 4019020. doi:10.1061/(asce)me.1943-5479.0000709.
Maqsoom, A., Choudhry, R. M., Umer, M., & Mehmood, T. (2021). Influencing factors indicating time delay in construction projects: Impact of firm size and experience. International Journal of Construction Management, 21(12), 1251-1262. doi:10.1080/15623599.2019.1613206.
Zarei, B., Sharifi, H., & Chaghouee, Y. (2018). Delay causes analysis in complex construction projects: A semantic network analysis approach. Production Planning & Control, 29(1), 29-40. doi:10.1080/09537287.2017.1376257.
Zaneldin, E. K. (2020). Investigating the types, causes and severity of claims in construction projects in the UAE. International Journal of Construction Management, 20(5), 385-401. doi:10.1080/15623599.2018.1484863.
Sinesilassie, E. G., Tabish, S. Z. S., & Jha, K. N. (2017). Critical factors affecting schedule performance: A case of Ethiopian public construction projects - Engineers’ perspective. Engineering, Construction and Architectural Management, 24(5), 757–773. doi:10.1108/ECAM-03-2016-0062.
Famiyeh, S., Amoatey, C. T., Adaku, E., & Agbenohevi, C. S. (2017). Major causes of construction time and cost overruns: A case of selected educational sector projects in Ghana. Journal of Engineering, Design and Technology, 15(2), 181–198. doi:10.1108/JEDT-11-2015-0075.
Al-Kharashi, A., & Skitmore, M. (2009). Causes of delays in Saudi Arabian public sector construction projects. Construction Management and Economics, 27(1), 3–23. doi:10.1080/01446190802541457.
Aziz, R. F. (2013). Ranking of delay factors in construction projects after Egyptian revolution. Alexandria Engineering Journal, 52(3), 387–406. doi:10.1016/j.aej.2013.03.002.
Jahangoshai Rezaee, M., Yousefi, S., & Chakrabortty, R. K. (2021). Analysing causal relationships between delay factors in construction projects: A case study of Iran. International Journal of Managing Projects in Business, 14(2), 412–444. doi:10.1108/IJMPB-01-2019-0020.
DOI: 10.28991/CEJ-2024-010-01-06
Refbacks
- There are currently no refbacks.
Copyright (c) 2024 Hijratullah Sharifzada, Yu Deming

This work is licensed under a Creative Commons Attribution 4.0 International License.